Location Dederang Terminal Station, Dederang
Schedule Feb 2014- June 2014
Project Detail
All civil works involved in constructing a new Transformer Slab at the Dederang Terminal station, including
- Excavation, Earthing and Conduit Installation
- Excavations, Formwork, Steel Tying, setting of rag bolts and concrete finishing of foundations
Excavation and installation of drainage system including pits, pipes and flame traps
Highlights/Challenges
- Working in and around a live environment
- Working with the client to complete set tasks effectively, safely and within the program time frame.
- Work carried out within the Terminal Station which included the essential use of height limited machinery and safety observers to complete the task safely and successfully
- Working successfully with other contractors our client used on site to ensure all works were carried out safely and communication was consistent over the project
Overall Performance
- Project delivered to clients requirements
- Safety – Nil LTI
- IR – no lost days due to industrial action