Location Berwick
Schedule May 2015
Project Detail
Civil Construct
- Lay to grade 630m of 355mm PE & 300mm pvc pipe
- Excavate trench to specified levels
Highlights/Challenges
- Managed the project on behalf of the client
- Traffic Management
- Communicating positively with local TAFE
- Trench depth of up to 4.5m- Shoring and shields required
Overall Performance
- Project delivered on budget and well before delivery date
- Safety – No incidents or injuries recorded on the project
- IR – no lost days due to industrial action