Location Riordans Rd, Tarrone North
Schedule May 2011- September 2012
Project Detail
Build 500KV Terminal Station from scratch in conjunction with other contractors
- Excavation and building bench
- Install drainage pipelines from 150mm – 1200mm pipe
- Installation of drainage pits
- Install concrete cable trench
- Install fire system
- Installation of Earthgrid
- Building of V drains & sediment pond
- Concrete Construction
Highlights/Challenges
- Leighroy’s Earthwork’s site supervisor was responsible for supervising/ advising other contractors onsite whilst building switchyard bench
- LREWX manager, Leigh Piggott took part in developing the programming requirements with the client to meet deadlines and budget
- Challenged by inclement weather
- Challenging material to work with whilst building the bench ( Volcanic Rock)
Overall Performance
- Project delivered on time and within budget
- Safety – No incidents recorded on the project